| Date |
Event |
| End of 2003 |
Building design completed |
| Spring 2005 |
Approval by Governor and Legislature |
| August 2005 |
Construction site preparation |
| September 2005 |
Mobilization begins |
| |
Demolition begins |
| |
Sitework begins |
| November 2005 |
Demolition completed |
| |
Foundation begins |
| December 2005 |
Sitework completed |
| January 2006 |
Foundation completed |
| |
Structure begins |
| Spring 2006 |
Building exterior begins |
| Summer/Fall 2006 |
Structure completed |
| Winter 2006 |
Paving and Landscaping begins |
| |
Building exterior completed |
| |
Paving and Landscaping completed |
| Summer/Fall 2007 |
Move-In and occupancy |
| Fall 2007 |
Construction completed (projected) |